Scheme updates

Wednesday 01 March
 
We are continuing to make good progress with the scheme and as of this week we have successfully installed 264 metres of new water main along Shrub Lane.
 
We are remain on track to complete phase one of the project by 23 March.

Shrub lane 2

Shrub lane 3

Wednesday 22 February 2017

We are making good progress with the scheme and to date we have successfully installed 230 metres of new water main north of the level crossing.

This week we’ve returned back to the level crossing to excavate for the connection which is planned for the beginning of March, following this we will return to laying the new main.

We are currently on schedule with phase one of the project.

Aa