Scheme updates

Friday 21 April

Work is progressing well and to date we have successfully laid 1125 metres of new pipeline along Shrub Lane and Battenhurst Road. 

We are now on track to complete phase two of the project slightly ahead of schedule in May.

Wednesday 29 March

Phase one of the scheme is now complete and tests are being carried out before the new section of pipe is connected to the water network

When these have been done we will need to backfill the large excavation with foam concrete. We anticipate that this will take place on Monday 3 April. This section of road can then be tarmacked and reopened as our work, and rolling road closure, continues further along Battenhurst Road.

There will be some activity on site over the weekend while we work on a new connection and we hope this will be completed by Tuesday 4 April.

Phase two of the scheme is now well underway and to date we have successfully laid 700 metres of new pipeline.

Wednesday 01 March
 
We are continuing to make good progress with the scheme and as of this week we have successfully installed 264 metres of new water main along Shrub Lane.
 
We are remain on track to complete phase one of the project by 23 March.

Shrub lane 2

Shrub lane 3

Wednesday 22 February 2017

We are making good progress with the scheme and to date we have successfully installed 230 metres of new water main north of the level crossing.

This week we’ve returned back to the level crossing to excavate for the connection which is planned for the beginning of March, following this we will return to laying the new main.

We are currently on schedule with phase one of the project.

Aa