Watt's Cross Road and Rings Hill, Hildenborough

Why are we doing this work?

To ensure our customers in the area continue to enjoy top quality and reliable tap water, South East Water will be laying 320 metres of new water main along Watt’s Cross Road and Rings Hill, Hildenborough.

The £75,000 scheme will allow South East Water to improve the capacity of the network and ensure we can continue to maintain water pressure to the area as the community grows.

Where are we working?

The new pipe will be laid along Watt’s Cross Road and Rings Hill, Hildenborough.

As a safety precaution for pedestrians, motorists and our contractor we need to close Watt’s Cross Road between the junction of Noble Tree Road to outside Oak Tree Farm.  The remaining works will then be undertaken using two way traffic lights.

Construction works will be carried out in stages, with the road being returned to its original state upon completion of one section before the working area moves along to the next stage.

Please be assured that access to homes and businesses will be maintained at all times.

When will the work take place?

The scheme is planned to start on Tuesday 3 January 2017 and is expected to take approximately nine weeks to complete. However our contractor’s staff will work as hard as they can to complete the work as quickly and safely as possible.

Work will take place during normal working hours, although there may be some activities at weekends. 