08 May 2017


The first 70 metre section of pipe has now been successfully installed along Castle Row, from the junction of Castle Street to the White Hart pub.

We are now working on the next section of water main between the pub and Age Concern and are aiming to complete this by the end of week commencing 8 May.

Following this we will move onto the third section of works where we will need to put a road closure back in place on Pin Hill. We are aiming to do this during the school holidays in order to minimise distribution.

We are currently still on schedule to complete the scheme by the end of July.

 

03 May 2017 

 

Our works along Castle Row are progressing well and we remain on schedule to complete the scheme by July. 

 

Castle row 1 

 

 Castle row 2

 

11 April 2017

 

The scheme is progressing well along the city wall carriageway with 200 metres of new pipe already in the ground via directional drilling and a further 100 metres still to be drilled. We have have also dug half the 50 metres of open cut excavation required.

 

Location of the work was moved from the opposite carriageway to the city wall side due to utilities congestion in the bus lane which meant it was impossible to dig there without seriously encroaching on the main carriageways.

 

 

 


Aa