Tilford Road_247px.jpgWork is underway on our programme of water mains upgrade work in the Hampshire area for the 2016/17 financial year.

Below is a provisional list of roads where work is planned to take place.

As preparations move forward, we will update this table with proposed start dates, durations and traffic management, however please be aware that this is a continually evolving programme therefore is subject to change.

Ahead of any work beginning we will endeavour to write to those residents and businesses which may be directly affected by our work. These letters will provide more specific information regarding the pipework installation which is to be undertaken and how we will work with the community to limit any disruption.

Hampshire:

Location Proposed
start date
Anticipated
duration
Proposed traffic
management

A287, Tadpole Lane and Ewshot Lane, Ewshot 30 August 2016 Until 27 April 2017 Temporary road closures

Reading Road, Mattingley  16 January 2017 Until 28 November 2017 Temporary road closure

Hawkley Road, Liss 23 January 2017 Until 23 March 2017 Temporary traffic lights

Fleet Road, Cove Road and West Heath Road, Farnborough  23 January 2017 Until 30 October 2017 Temporary road closures, traffic lights and lane closures

Whitedown Lane, The Butts, Butts Road and Selborne Road, Alton  23 January 2017 Until 30 October 2017 Temporary traffic lights 

Gresley Road, Basingstoke 13 February 2017 Until 20 March 2017 Temporary footpath closure

Hatch Warren Roundabout, Basingstoke 20 February 2017 Until 6 June 2017 Temporary traffic lights

Station Road, Hook TBC TBC TBC