Warfield Street, Warfield

Why are we doing this work?

To ensure our customers in Warfield continue to enjoy top quality tap water, South East Water will be laying a new water main in the area.

Work on the £14,000 scheme, approximately 18 metres in length, will begin on Monday 8 May and the project is expected to take two weeks to complete.

Where are we working?

Work to install the new water main will take place within the carriageway at the crossroads of Warfield Street, Osborne Lane and Newell Green.

Due to the restraints of working in the carriageway, we will be using open cut techniques.

As a safety precaution for pedestrians, motorists and our contractor, temporary traffic lights will be in operation for two weeks.

Work will take place during normal office hours however some work may also take place at weekends.