Binfield Road, Bracknell

Why are we doing this work?

As part of an ongoing programme to improve our water supply network we are planning a scheme to install 255 metres of pipe along Binfield Road, Bracknell from the Western Roundabout.

This work is necessary to improve the capacity of the network and ensure we can continue to maintain water pressure to the area as the community grows.

When and where are we working?

Work on the £70,000 scheme to install the new water main will take place along Binfield Road, Bracknell.

This will begin on Monday 13 March 2017 and is anticipated to take approximately eight weeks to complete. However our contractor will be working as hard as they can to complete the work as quickly and safely as possible.

How can we ensure this work is done with minimum disruption to you?

As a safety precaution for pedestrians, motorists and our contractor a temporary one-way system via Wokingham Road and Downshire Way will be in place for the duration of the scheme.

We appreciate this will be inconvenient for residents but our contractor’s staff will be working as quickly as safely as possible to complete this work.

Access to homes and businesses will be maintained at all times.

Work will take place during normal office hours however some work may also take place at weekends.